St. Luke’s Church, London

St Luke’s is a church in a residential area and mixed-use developments. The construction of is traditional London brick, with a timber frame roof trusses and concrete floor slab.

The surrounding area had a mixture of retail and commercial premises with a high density of cafes, restaurants and bars and neighbourhood relations were planned and executed to achieve a harmonious environment

Prior to the works being carried out, Tower Demolition coordinated a demolition and refurbishment survey to ascertain the presence of asbestos and the best process for removal. An architectural salvage survey was also conducted and we produced a salvage plan

The main H&S issues were working at height and unplanned collapse. The access and egress was via the main site entrance off Havannah Street. Tower Demolition co-ordinated the site team, establishing a process to bring vehicles to and from site in such a way that minimised reversing manoeuvres.

Care was taken to minimise noise, vibrations and dust nuisance as office operations were ongoing during demolition works. A vehicle movements management plan was developed to ensure undisturbed access and operation of on-site office activities.

To achieve 100% success Tower Demolition Limited always ensure that all operatives working on site receive a Health and Safety induction before starting work. Regular meetings were held between all those working on site to exchange information on project progress, health and safety matters.

This project was delivered on time and in budget and Tower successfully recycled 100% of the demolished structure.

Disclaimer: The above projects were conducted by Tower under the direction of James Bibbey and John Egan joint managing directors of Tower Demolition (Holdings) Ltd, formerly Tower Demolition and Enabling Ltd, formerly Tower Demolition (Holdings) ltd, formerly Tower Demolition Ltd, this project was not conducted by BibbEgan Demolition and Strip Out ltd nor BibbEgan Group ltd or any of its subsidiaries.

Project Details

CLIENT

St. Luke’s Church

PROJECT TYPE

Residential

DURATION

6 Weeks

PROJECT VALUE

£90,000

TYPES OF WORK
  • Refurbishment & Demolition Survey

  • Asbestos removal

  • Services Disconnections

  • Soft Strip

  • Architectural Salvage

  • Top Down Demolition

  • On-site Segregation/ Recycling

  • 100% Recycling