Jubilee Avenue, Highams Park E4
Jubilee Avenue was a four acre site containing large two-storey warehouses and offices. The warehouse construction was brickwork walls and steel frame roof clad in asbestos cement sheeting. Tower Demolition was engaged to conduct the demolition and site clearance.
The scope of works covered service disconnections; site hoarding; asbestos removal; strip out; scaffolding; remote demolition and on site crushing.
Tower Demolition’s Project Management Team coordinated the entire project working closely with our independent H&S advisor, MEL and the Health & Safety Executive.
The removal of all asbestos containing materials involved full enclosures including scaffolding access and protection. An independent air testing company conducted parameter air testing for the entire duration of the project.
The soft strip of internal offices and main buildings was conducted by one foreman and 12 operatives. The demolition of all remaining structures was then undertaken with onsite crushing of the resulting debris which was stockpiled for reuse.
Tower Demolition’s 360<sup>0</sup> demolition excavators were used during the remove demolition phase of the project. Also on the project was a QJ340 Sandvik Mobile Crusher. Metal and all recyclable materials were segregated from all other arisings and taken away for recycling. Tower Demolition endeavour to recycle 90% of all suitable demolition debris.
Care was taken to minimise noise, vibrations and dust nuisance along with a traffic plan for vehicle movement on and off site in such a way as to alleviate any impact onto the surrounding roads.
Project Details
CLIENT
Wrenbridge Land Limited
PROJECT TYPE
Commercial
DURATION
12 Weeks
PROJECT VALUE
£297,000
TYPES OF WORK
Disclaimer: While the above project was not conducted by BibbEgan Group, it was carried out under the direction of James Bibbey & John Egan who were managing directors of the contractor, Tower Demolition.