CASE STUDY

No.1 Berkeley Street, Holiday Inn

Project Particulars

Client:

Crosstree | Jackson Coles

Principal Contractor:

BibbEgan Group

Project Value:

£1,700,000

Duration:

24 Weeks

Project details

We delivered a phased strip out project at No.1 Berkeley Street in Piccadilly for Crosstree and Jackson Coles. The first phase involved office premises across the first to fourth floors, situated between busy retail units with occupied hotel rooms above. The second phase comprised a full strip out of the Holiday Inn’s 198 bedrooms and roof and basement plant rooms, returning the hotel to shell and core.

Working in a busy central London location required careful control of construction traffic, noise and pedestrian safety. We agreed reduced noisy working hours and coordinated loading and unloading times with affected neighbours to minimise disruption to surrounding businesses.

Our responsibilities included temporary works coordination, structural support design and installation, together with full soft and mechanical strip out. Asbestos containing materials were removed using routes separate from those shared with other occupiers.

Non load bearing walls and areas of screed were demolished by hand. We applied the same controlled approach when removing the canopy from the building’s front façade.

Maintaining essential services to the occupied hotel and neighbouring retail units was a priority during the office works. Our service engineers traced and isolated supplies within the working areas back to the internal risers, preserving live feeds to surrounding occupiers.

Temporary lighting and transformers supported the works following service removal. Waste was segregated on site, with 97% of project arisings recycled.

Scope of works

  • Refurbishment and demolition survey
  • Asbestos removal
  • Service disconnections
  • Scaffolding
  • Crane lift
  • Soft strip out
  • Hard strip
  • Plant removal
  • Lift removal
  • On site waste segregation and recycling
  • Temporary structural support design
  • Temporary support installation
  • 97% recycling