Project Particulars
Client:
GPE for The Crown Estates
Principal Contractor:
BibbEgan Group
Project Value:
£600,000
Duration:
16 Weeks
BibbEgan delivered asbestos removal and soft strip works at Egyptian and Dudley House, Grade II listed buildings owned by The Crown Estate on Piccadilly in central London.
We stripped both buildings back to their structure, working from the basement to Level 6, together with Level 7 in Dudley House and roof plant at Egyptian House. Ground floor works were limited to the reception areas, allowing the existing retail units to remain operational.
With no records of existing services available, we traced and identified supplies before isolating those serving the work areas. Investigations outside normal working hours enabled us to identify and tag services supplying the occupied shops, maintaining their operation throughout the project.
Decades of successive office fit outs had created multiple layers of stud walls, floor finishes and plywood. These generated considerably more waste than anticipated, requiring careful storage and segregation before removal. With special permission from Westminster, we loaded out debris during the early morning to minimise disruption to pedestrians and traffic on Piccadilly. We achieved a recycling rate of 96%.
We removed all known asbestos throughout both buildings, including asbestos insulating boards forming the lift shafts at every level. Additional asbestos discovered during the works required us to adapt our sequence and coordinate closely with other trades undertaking fit out works on floors already stripped.
A detailed pedestrian and traffic management system controlled deliveries and collections at the front of the buildings. This also accommodated daily deliveries to the occupied shops, allowing neighbouring businesses to continue trading throughout a demanding project.