Project Particulars
Client:
WeWork
Principal Contractor:
BibbEgan Demolition
Project Value:
£740,000
Duration:
12 Weeks
BibbEgan delivered a 20,000m² soft strip project for WeWork at 125 Shaftesbury Avenue, an island site in London’s West End.
Heavy traffic along Shaftesbury Avenue and the surrounding one way streets made site logistics particularly challenging. Before works began, we developed a detailed traffic management plan to coordinate deliveries and skip collections, minimising disruption to road users, pedestrians and neighbouring businesses.
The client required the finished offices to be available to let by September 2018, with our works commencing in January that year. To support this programme, we worked double shifts, seven days a week, completing the soft strip of the office floors within ten weeks. Basement plant removal was completed two weeks later, bringing our works to a total of twelve weeks.
Our scope also included service disconnections, the erection of a scaffolding gantry and installation of a temporary fire alarm system. Through on site waste segregation and recycling, we achieved 100% diversion from landfill for the demolition arisings.