Project Particulars
Client:
Fragrance Group
Principal Contractor:
BibbEgan Demolition
Project Value:
£3,500,000
Duration:
30 Weeks
We delivered a 45,000 m² strip out project for Fragrance Group at the former Holiday Inn Forum Hotel on Cromwell Road, Kensington. The works extended across 30 floors in a sensitive residential setting, requiring careful management of noise, logistics and neighbouring properties.
Our first priority was to establish a fully hoarded site, separating the works from surrounding residents. Daily noise monitoring helped us manage disruption throughout the programme.
Working with our specialist MEP contractor, we completed detailed service tracing and identification before isolating incoming supplies back to their heads and meters.
The extensive soft strip covered almost 1,000 hotel rooms, corridors, communal areas, bars and restaurants, together with roof and basement plant. Waste was transferred down the lift shafts to the loading bay and car park, where a 14 tonne excavator fitted with a selector grab loaded materials into 40 cubic yard containers.
Following the soft strip, we removed selected brick and block walls, service risers and floor slabs across the building. The wider package also included asbestos removal, a new goods lift and lift pit, below ground drainage, fire protection and temporary safety systems.
We completed the project on time and within budget, with no complaints from neighbouring residents.