CASE STUDY

St George’s Hospital

Project Particulars

Client:

NHS Trust

Principal Contractor:

BibbEgan Group

Project Value:

£2,000,000

Duration:

20 Weeks

Project details

BibbEgan delivered a major demolition project at St George’s Hospital in Tooting during the height of the Covid pandemic. Working within an operational hospital, we carefully coordinated our activities to protect patients, staff and essential services.

Dust control was particularly critical, as hospital wards needed to keep windows open to improve ventilation. We used advanced demolition equipment alongside rigorous dust suppression and monitoring to control airborne particles and demonstrate the effectiveness of our measures.

The works also involved demolishing buildings immediately beside the hospital’s main oxygen tanks, which supplied intensive care wards operating at full capacity. Close liaison with hospital management and facilities teams was essential throughout the project.

We established a fully hoarded site, with traffic marshals positioned at the front and rear of delivery vehicles to escort them safely into the working area. Before demolition began, we traced and identified existing services, isolating only those supplying the buildings scheduled for removal while maintaining supplies to the operational hospital.

A comprehensive asbestos removal programme was completed under controlled conditions, with operatives, asbestos waste and decontamination facilities screened from public view. We then undertook soft strip and demolition works, segregating materials on site and achieving a recycling rate of 99%.

Scope of works

  • Refurbishment and demolition survey
  • Principal Contractor duties
  • Asbestos removal
  • Liaison with hospital management
  • Liaison with the hospital facilities team
  • Rigorous dust monitoring and suppression
  • Soft strip
  • Demolition
  • On site waste segregation and recycling
  • 99% recycling rate