Project Particulars
Client:
Marks & Spencer | Audas
Principal Contractor:
BibbEgan Group
Project Value:
£1,300,000
Duration:
20 Weeks
We delivered a phased strip out and enabling works project at M&S Whetstone in North London, supporting the store’s expansion into the neighbouring former Carpetright premises and refurbishment of the existing Marks & Spencer building.
The buildings featured traditional masonry and steel frames, with profiled steel sheeting to the roof and sections of the façade. Following vacant possession, we secured the site with Heras fencing and installed service isolations and temporary supplies to support safe working across both premises.
The first phase focused on stripping out the former Carpetright building, removing internal partitions, ceilings and M&E installations to leave an isolated shell ready for fit out. Roof maintenance included replacing fixings and applying a liquid coating.
During the second phase, we moved into the existing M&S premises. Detailed verification and tracing of electrical and gas services identified supplies that needed to remain live throughout the works.
We removed floor, wall and ceiling finishes, internal partitions, back of house kitchen facilities and WC areas, returning the premises to shell condition for the incoming fit out contractor.
The wider package included temporary works, groundworks, wall demolition, roofing works, external façade improvements and drainage remediation, preparing both buildings for the store’s next stage of development.