CASE STUDY

Procession House, Ludgate Hill

Project Particulars

Client:

Tower8

Principal Contractor:

BibbEgan Demolition

Project Value:

£3,400,000

Duration:

48 Weeks

Project details

We delivered a phased strip out and partial demolition project at Procession House on Ludgate Hill for Tower8, enabling the refurbishment and extension of the office accommodation. The reinforced concrete building comprised eight levels, including the roof and basement, and spanned City Thameslink station and several retail units at the junction of two busy London roads.

Our works included a complete soft strip with mechanical and electrical removal, utility service tracing and termination, lift removal and partial structural demolition. We managed temporary works design, coordination and installation, combining the existing structure with RMD support props to provide a specialist temporary support scheme.

Working closely with the client’s nominated scaffolding contractor, we oversaw the installation of a fully enclosed external scaffold with Monarflex sheeting, together with a passenger hoist and multiple beam hoists. We also provided and maintained weather protection throughout the works.

Temporary propping enabled façade sections to be demolished and prepared the building for floor plate extensions by subsequent contractors. We cut back roof areas to allow new structural steelwork to be installed and removed substantial rooftop planters extending approximately 200 metres around the building.

Close liaison with the Corporation of London, Transport for London, Network Rail and the Mayor of London’s office supported approvals before each stage commenced. The programme also required coordination with the City of London Police to accommodate the Lord Mayor’s Show.

Maintaining services to the operational station and retail units was essential. We identified and retained plant serving occupied areas and protected fire escape routes. Fire alarm and evacuation arrangements remained operational and interconnected with the station and retail alarm systems throughout the works.

Each phase was handed over within the programme timescales, with waste segregated on site and 99% of project arisings recycled.

Scope of works

  • Refurbishment and demolition survey
  • Asbestos removal
  • Temporary works design
  • Temporary works coordination
  • Temporary works installation
  • Demolition
  • Weather protection
  • On site waste segregation and recycling
  • 99% recycling